1. New Bridge Road
(Right Most Lane-from under Garden Bridge to Temple St)
On 02/01/2020 from 8.00pm to 2.00am the following day
(For rehearsal and set-up)
2. New Bridge Road
(Left Most Lane-between Pagoda St & Temple St)
On 03/01/2020 from 8.00pm to 1.00pm the following day
(For rehearsal and set-up)
3. New Bridge Road
(between Upper Cross Street and Kreta Ayer Road)

4. Eu Tong Sen Street

On 04/01/2020 from 1.00pm to 12.00 midnight
(For opening ceremony)
5. Pagoda Street

6. Temple Street

7. Trengganu Street

8. Sago Street

9. Smith Street

(a) From 03/01/2020 to 04/01/2020 (both dates inclusive) during the following days and hours:
Day Time
(i) Monday to Friday 6.00pm to 11.00pm
(ii) Saturday and Sunday and eve of public holiday 6.00pm to 12.00 midnight
10. New Bridge Road
(Right Most Lane)
On 22/01/2020 from 8.00pm to 2.00am the following day
(For rehearsal and set-up)
11. New Bridge Road
(Left Most Lane-between Pagoda St & Temple St)
On 23/01/2020 from 8.00pm to 5.00pm the following day
(For rehearsal and set-up)
12. South Bridge Road
(Right Most Lane-Upper Cross St to Sago Lane)
On 24/01/2020 from 11.00pm to 1.00am the following day
13. New Bridge Road
(between Upper Cross Street and Kreta Ayer Road)

14. Eu Tong Sen Street

On 24/01/2020 from 5.00pm to 3.00am the following day
(For Countdown Celebrations)
15. New Bridge Road
(Right Most Lane-from under Garden Bridge to Temple St)
On 01/02/2020 from 8.00pm to 2.00am the following day
(For rehearsal and set-up)
16. New Bridge Road
(Left Most Lane-between Pagoda St & Temple St)
On 01/02/2020 from 8.00pm to 2.00pm the following day
(For rehearsal and set-up)
17. New Bridge Road
(between Upper Cross Street and Kreta Ayer Road)

18. Eu Tong Sen Street

On 02/02/2020 from 2.00pm to 11.00pm